The "Precision Diagnosis and Remote Diagnosis Management" project is2014years11The "Precision Diagnosis and Remote Diagnosis Management" project was fully launched at Shandong Huadian Longkou Power Generation Co., LTD. (Longkou Power Plant). After nearly three months of intense construction, the project team successfully completed the relevant work of the project.
In accordance with the project implementation requirements, Longkou Power Plant, based on the actual situation of the plant and the critical grades of the equipment, has#3,#4,#5,#6It was selected from the crew302All equipment is included in the scope of the precision overall inspection, which encompasses the boiler area, turbine area, ash water area and transfer equipment in the common area152Electrical equipment such as platforms, step-up substations and transformers150"Platform.
in152Among the transfer equipment, there are a total of those with relatively serious defects that require planned maintenance3A unit with minor defects that require local adjustment36A platform where problems are not obvious and require trend monitoring58A device that is operating normally15The platform, among which#3The furnace#2Coal mill#4machine#8Low-pressure drain pump#5The furnace#4Coal mill3This piece of equipment has a relatively serious defect. in150Among the electrical equipment, there are a few with minor defects2A device that is operating normally134The device was not inspected due to shutdown14"Platform.
The implementation steps of precise inspection
Phone
Code