The "Equipment Reliability and Life Extension Management" project (Precision Inspection) is2014years10At the beginning of the month, the project was fully launched at Guodian Nanning Power Generation Co., LTD. (Nanning Power Plant). After nearly three months of intense construction, the project team successfully completed the relevant work.
In accordance with the project implementation requirements, based on the actual situation of Nanning Power Plant and the critical grades of the equipment, from#1,#2It was selected from the crew336All equipment is included in the scope of the precision overall inspection, including boilers, turbines, chemical equipment, coal conveying equipment, and transfer equipment in the desulfurization area200Electrical equipment such as platforms, step-up substations and transformers136"Platform.
in200Among the transfer machine equipment, there are a total of those with serious defects that require immediate repair1A unit with relatively serious defects that require planned maintenance13A unit with minor defects that require local adjustment45A platform where problems are not obvious and require trend monitoring62A device that is operating normally45The platform, among which#1Furnace induced draft fan sealing fan, fuel oilAOil supply pump#7Head belt coal conveyor#2AVacuum pump#1BCooling pumps, etc8Equipment with relatively serious defects. in136Among the electrical equipment, there are many with serious defects1The common defect of the platform13A device that is operating normally101"Platform.
In order for the power plant to persistently carry out the "Equipment Reliability and Life Extension Management" project (precision inspection) and make it an important part of equipment management, we have helped the power plant establish relevant organizational systems, work processes, management standards, technical standards and other management documents and systems. It provides a management foundation and institutional guarantee for "Equipment reliability and life extension management" (precise inspection).
Precise inspection and resolution7Big problem
1. All auxiliary machines are fully under condition-based maintenance.
2. Reduce98%Non-shutdown and load reduction accidents;
3. Eliminate emission accidents;
4. The major overhaul time of the mainframe has been extended2-6"Year;"
5. The operation and maintenance costs have decreased30%;
6. Establishment of a digital, networked and intelligent control platform;
7. Unified scheduling of human resources within the region, and sharing of fault information and solution resources.